AI Analyst Helm

Ask questions about your mining operations data

START WITH
Production Data
View historical production metrics
Variance Analysis
Analyse performance against targets
Explore Metrics
Discover available data points
Enter Type your question below or pick a suggestion above
#1
Show me budget Waste Mined Opex, Waste Mined (Capex) and ROM Production for FY27 by month as a stacked bar chart
Just now
Understanding Request
The user wants budget data for three metrics: Waste Mined Opex, Waste Mined Capex, and ROM Production for FY27 by month
1.3s
Searching Entities
Found results for “Waste Mined Opex, Waste Mined Capex, ROM Production”
1.9s
Fetching Data
Fetched WASTE_TONS and ROM Production for the FY27 budget
1.7s
Building Visualisation
Chart prepared
40ms
≡
FY27 Budget - Waste Mined Opex, Waste Mined Capex & ROM Production
April 2026 – March 2027 (Monthly Budget)
Tons (kt)
6,000K
5,000K
4,000K
3,000K
2,000K
1,000K
0K
Apr 26May 26Jun 26Jul 26 Aug 26Sep 26Oct 26Nov 26 Dec 26Jan 27Feb 27Mar 27
Waste Mined Opex Waste Mined Capex ROM Production
ANALYSIS SUMMARY

Here’s the FY27 budget stacked bar chart for all three production metrics across the 12 months. A few key observations:

  • Total mined volume is heavily skewed - June 2026 stands out with the highest Waste Mined Capex (~1.95Mt) but almost zero Opex waste, suggesting a major capital stripping campaign planned for that month.
  • Waste Mined Opex dominates most months, peaking in April and July–August 2026 (~1.5–1.6Mt), with a significant dip in June and September.
  • ROM Production is relatively modest compared to waste volumes, with its strongest months in September and February 2027 (~659kt and ~605kt respectively).
  • The total budgeted stack per month ranges from roughly 1.5Mt to 2.3Mt, with June 2026 being the single largest planned production month.
I want to test if this budget is achievable. We have 9 haulers operating at 1,200 tph, for 15 hrs/day. From November – March we lose 6 days per month to rain. Check we have sufficient hauling capacity each month to achieve the budget total tons for FY27, and show me the shortfall.
Just now
Understanding Request
The user wants to check if the budget is achievable given hauler capacity constraints
2.4s
Searching Entities
Resolved WASTE_TONS & ROM Production at Production level
2.1s
Fetching Data
Fetched budget total tons (Opex + Capex + ROM) for FY27, monthly
1.9s
Running Analysis
Computing monthly hauler capacity × available days, subtracting rain loss, comparing vs budget tons…
3.4s
Building Visualisations
Charts prepared · capacity vs budget, cumulative shortfall, monthly breakdown table
40ms
≡
Monthly Hauling Capacity vs Budget Total Tons – FY27
9 haulers × 1,200 tph × 15 hrs/day = 162,000 tons/day  |  Nov–Mar: 6 rain days/month
Tons
6.0M
5.0M
4.0M
3.0M
2.0M
1.0M
0
Apr 2026May 2026Jun 2026 Jul 2026Aug 2026Sep 2026 Oct 2026Nov 2026Dec 2026 Jan 2027Feb 2027Mar 2027
Hauling Capacity Budget Total Tons
≡
Cumulative Monthly Shortfall – FY27
Positive = shortfall (budget exceeds capacity)  |  Negative = surplus
Tons
3.0M
2.4M
1.8M
1.2M
600K
0
–600K
Apr 2026May 2026Jun 2026 Jul 2026Aug 2026Sep 2026 Oct 2026Nov 2026Dec 2026 Jan 2027Feb 2027Mar 2027
Cumulative Shortfall (Tons) Cumulative Shortfall (Hours)
Hauler Capacity Analysis – Detailed Monthly Breakdown – FY27
FY27 Total Capacity: 54,270,000 tons  |  Budget: 56,929,651 tons  |  Net Shortfall: (2,659,651) tons
Month Calendar Days Rain Days Available Days Hauling Capacity Budget Tons Surplus / (Shortfall) Required Hrs
Apr 2026300304,860,0004,686,840173,160434.0
May 2026310315,022,0005,063,041(41,041)468.8
Jun 2026300304,860,0004,793,88366,117443.9
Jul 2026310315,022,0005,466,635(444,635)506.2
Aug 2026310315,022,0005,498,594(476,594)509.1
Sep 2026300304,860,0005,146,062(286,062)476.5
Oct 2026310315,022,0005,142,199(120,199)476.1
Nov 2026306243,888,0004,532,428(644,428)419.7
Dec 2026316254,050,0004,216,015(166,015)390.4
Jan 2027316254,050,0003,970,91979,081367.7
Feb 2027286223,564,0004,132,294(568,294)382.6
Mar 2027316254,050,0004,280,741(230,741)396.4
TOTAL3653033554,270,00056,929,651(2,659,651)5,271.4
Show me FY27 budget by month as a stacked bar chart… Analysing… Ask AI Analyst anything about your operations… Show me budget Waste Mined Opex, Waste Mined (Capex) and ROM Production for FY27 by month as a stacked bar chart I want to test if this budget is achievable. We have 9 haulers operating at 1,200 tph, for 15 hrs/day. From November – March we lose 6 days per month to rain. Check we have sufficient hauling capacity each month to achieve the budget total tons for FY27, and show me the shortfall.
WMC Model – Forecast Model Complex reasoning ⌘↵ to send · / for commands