Waste Mined Opex (Tons) - New Prospect Mine | Budget vs Actual (FY26)
Monthly | Apr 2025 – Mar 2026
Tons
Apr 2025May 2025Jun 2025
Jul 2025Aug 2025Sep 2025
Oct 2025Nov 2025Dec 2025
Jan 2026Feb 2026Mar 2026
Actual
Budget
Here's the chart for Waste Mined Opex (Tons) at New Prospect Mine, comparing Actual vs Budget across FY26.
Key takeaways:
- Actual waste mined came in below budget every month — total actual was ~23.7M tons vs ~30.6M tons budgeted, a shortfall of roughly 22%.
- The largest absolute gaps were in April 2025 (~2.1M actual vs ~3.16M budgeted) and August 2025 (~1.95M vs ~2.82M).
- Actual output held in a tight band of ~1.8–2.2M tons month-on-month, indicating consistent operational tempo. March 2026 (~94% of plan) and January 2026 (~90%) tracked closest to budget.